Will the U.S. Stop Building AI Data Centers? Can It Afford To?

中文English

After U.S. stocks fell sharply on November 5, discussion of a pause in data center construction intensified again.

Texas had already directed its environmental regulator on September 21 to pause data center-related permits pending a grid audit. That is a regional measure, not evidence that the United States will impose a nationwide, long-term halt on computing infrastructure. The more useful questions are what a broad construction freeze would cost, and which projects actually need to slow down.

1. Why a prolonged nationwide halt would be costly

Adding up the companies' own capital expenditure measures, Microsoft, Amazon, Alphabet and Meta reported approximately $208.7 billion in capital expenditure in the third quarter of 2026, about 84.2% more than a year earlier. Their full-year guidance totals roughly $730 billion when ranges are taken at their midpoints. These are global figures covering servers, data centers, networks and other business investment, with differences in lease accounting. They cannot all be counted as U.S. AI data center investment, but expansion is already reflected in actual spending.

Revenue at the leading providers is also growing. Microsoft Cloud generated $63.9 billion in quarterly revenue, up 30% year over year, while Azure grew 48%. AWS revenue reached $46.0 billion, up 39%, and Google Cloud reached $30.7 billion, up 103%. The business definitions differ, but together they show demand for enterprise cloud migration, storage and AI services. Google Cloud also includes TPU system sales, so not all of its growth can be attributed to model training or rented computing capacity.

Data centers train and run AI, but they also host enterprise software, storage and everyday cloud services. JLL's North America midyear report, published in August, put data center capacity under construction at approximately 66 gigawatts, measured in power capacity. About 95% was pre-committed, while market vacancy had remained near 1% for three consecutive years. Such commitments do not guarantee that every project will be delivered on time, but they indicate identified demand behind a substantial share of construction.

If usable computing capacity is approaching its limit while new supply is frozen for an extended period, training queues could lengthen and the launch of enterprise AI applications, automated customer support and inference services could slow. For contracted projects with clear demand and little alternative capacity, delays would affect service delivery, not just distant expansion plans.

Operating data centers could continue running, but the room to accommodate new customers and new model generations would narrow. Slower construction could also reduce orders for servers, uninterruptible power supplies, transformers, cooling equipment and engineering work, affecting investment and employment across those supply chains.

High spending, however, does not make every project commercially sound. Some connection applications may still lack confirmed customers or financing. A nationwide halt would be costly, but that does not justify approving every proposal. Expansion backed by real demand, reliable power and reasonable expected returns is the part that would be hardest to pause.

Q3 capital expenditure, 2025 versus 2026, in US$ billion: Microsoft 34.9 and 45.2; Amazon 35.095 and 77.259; Alphabet 23.953 and 51.355; Meta 19.374 and 34.906. Company-reported measures roughly total $113.3bn and $208.7bn, up 84.2%. Global investment, not solely U.S. AI spending.
Calendar Q3 compared within each company. Lease treatment differs, so the aggregate is approximate. Figures cover global investment, including non-AI and other businesses, rather than only U.S. AI facilities.

2. Funding a data center does not guarantee power

ERCOT, the operator covering most of the Texas grid, reported in June that large-load connection requests exceeded 438 gigawatts, with nearly 89% coming from data centers. Those are applications, including projects that may never proceed. They are not existing electricity demand or a measured power shortfall.

A data center needs electricity delivered reliably at a particular location and time. Even if national generation is sufficient in aggregate, the lines, substations and power sources serving a specific site may not support its additional demand.

The contiguous United States has three major interconnections: Eastern, Western and ERCOT, which covers most of Texas. Power exchange between them is limited. Electricity can move across state lines within each system, but transmission capacity and operating constraints still apply. Surplus power elsewhere is not necessarily available to a data center when it needs it.

Generation, transmission upgrades and data center commissioning also need compatible schedules. If the building and servers are ready before electricity can be connected, assets may sit idle and revenue may be delayed.

Yet the grid cannot simply expand to meet the full volume of applications. Developers may apply at several locations or reduce projects as demand and financing change. If utilities build for the highest requested load and too few users materialize, construction costs may not be recovered as planned. Other electricity customers could be left with part of the remaining bill.

What becomes idle in that case may be a line, substation or capacity reserved for expected demand. It does not mean an equivalent quantity of electricity has already been generated with nowhere to go. Transmission constraints can prevent surplus generation from supporting a tight market; demand that fails to materialize can leave new infrastructure without its intended users. These are distinct planning risks.

In September, ERCOT made completed verification a condition for inclusion in its first batch of connection assessments. Checking project maturity, phased demand and local grid capability can bring investment closer to realistic needs.

Areas with tight supply therefore face a two-sided problem: too little preparation can delay genuine projects, while too much can leave idle infrastructure. Matching power system development to computing expansion is an essential part of continuing construction.

3. How data centers can affect household electricity bills

Preliminary U.S. Energy Information Administration data show that the average residential retail electricity price rose from 17.03 cents per kilowatt-hour in January–August 2025 to 18.19 cents in the same period of 2026, an increase of 6.8%. Regional differences were substantial. In August alone, prices rose approximately 11.3% year over year in Virginia and 10.4% in Ohio, while New Jersey, also within PJM's service footprint, recorded a decline of about 0.4%.

Data centers can raise supply costs when large new loads cluster in places where generation and transmission are already constrained. Besides buying additional electricity, the system must secure enough generating capability to be available during peak demand. That creates capacity costs.

In July, PJM's capacity auction for the 2028/29 delivery year cleared at the price ceiling of $325 per megawatt-day, approximately 2.5% below the previous round. Even after counting other committed resources recognized under the rules, the capacity secured at that point remained 6,831 megawatts below the reliability requirement. A small price decline did not mean that the supply challenge had eased to the same extent.

That gap concerned future peak-period reliability reserves. It was not a current electricity shortage or a guarantee of future blackouts. Price caps and capacity accreditation rules also affect auction prices, so the resources actually secured must be considered alongside price signals.

For the earlier 2025/26 delivery year, PJM's independent market monitor estimated that data center load accounted for approximately $9.3 billion of the increase in capacity auction revenue, roughly 75% of that auction's total increase. This indicates a substantial effect on regional capacity costs. It does not mean household electricity prices rose 75%.

New loads increase demand for limited generation and may require new lines and substations. Energy procurement and capacity costs can enter customer bills through supply contracts. How grid investment is recovered depends on connection charges, rate allocation and regulation. Requiring data centers to pay the relevant connection and expansion costs can reduce subsidies from other customers, but may not fully offset market price effects when supply is tight.

Fuel prices, weather, generator availability and rate adjustments also affect electricity prices. The observed increases cannot all be attributed to data centers. Where generation and network capacity are abundant, an additional customer paying its full costs can instead spread existing fixed costs across a larger base. The key questions are which costs a project adds, whether new supply accompanies it and who ultimately pays.

U.S. average residential retail electricity price: 17.03 cents/kWh in January–August 2025 and 18.19 in the same period of 2026, up 6.8%. Separately, August year-over-year changes: Virginia +11.3%, Ohio +10.4%, New Jersey -0.4%. The time windows differ. These changes do not identify AI causation. EIA preliminary 2026 data.
Top: national January–August average prices. Bottom: state-level August year-over-year changes. The windows differ. Fuel, weather, procurement and rates also affect prices; these are not estimates of data centers’ causal contribution.

4. How China and the U.S. arrange power supply and pricing

China's electricity market recorded 1,303.7 billion kilowatt-hours of interprovincial and interregional transactions in the first three quarters of 2026, up 9.1% year over year. Transmission links and trading arrangements help allocate electricity across a wider area. A comparison with the United States nevertheless needs to distinguish household tariffs, business power procurement and connection to individual sites.

Chinese households pay regulated catalog tariffs, with policy emphasizing basic price stability. Data centers mainly buy electricity under commercial and industrial arrangements, using medium- and long-term contracts to manage price risk alongside spot and green power transactions. Household tariffs do not automatically move in step with corporate procurement costs. U.S. residential prices are also influenced by regulation and supply contracts. The difference lies in the rules and timing of cost transmission, rather than one country having fixed prices and the other unrestricted market fluctuations.

China's ultra-high-voltage transmission network and system of unified dispatch with management at different levels provide tools to coordinate generation, transmission and demand. Clean electricity from western regions can be transmitted elsewhere or support nearby computing facilities. Transfers still depend on available transmission capacity, trading arrangements and secure grid operation.

The East Data, West Computing initiative also adjusts where demand is located, directing workloads with lower latency requirements that are suitable for remote processing toward regions rich in clean energy. Siting decisions must still balance network latency, distance from customers and power reliability.

The United States is also developing data centers in more energy-abundant locations, rather than placing all new load in established hubs. In some constrained markets, however, power that can actually be delivered cannot be expanded quickly. This makes capacity price pressures and disputes over community costs more likely.

China's cross-regional allocation tools and coordination between computing and power can broaden the options for siting and supply. Stable residential tariffs do not make additional system costs disappear. Both countries need generation, transmission and data center commissioning to advance on compatible schedules. Regional transfers can ease some bottlenecks, but do not replace scrutiny of local connections and project returns.

5. China keeps building. What if the U.S. slows down?

By June 2026, China's computing facilities in operation had reached 15.56 million standard rack equivalents. The National Energy Administration reported on October 30 that electricity use by internet data services rose 41.6% year over year in the first three quarters. Both measures include non-AI activity, but show the scale of the infrastructure and demand already in place.

Construction is continuing. Progress reported in October showed more than 110,000 standard rack equivalents operating in Qingyang, Gansu, with several data centers still under construction. An intelligent computing center in Inner Mongolia had also entered the handover stage and is intended to serve the Beijing–Tianjin–Hebei region.

Future plans are explicit as well. The Ministry of Industry and Information Technology's 15th Five-Year Plan for the information and communications sector calls for intelligent computing capacity to grow by more than 500% between 2025 and 2030, alongside coordinated development of computing facilities, networks and electricity supply. This is a future target, dependent on equipment, power and customer demand, rather than completed capacity.

If new U.S. computing capacity remains constrained while China continues converting electricity, chips, networks and customer demand into usable capacity, the United States could face greater competitive pressure in model iteration, service expansion and delivery costs.

That pressure would accumulate over time. With the necessary talent, software and demand, more usable computing capacity can support more experiments and service deployments, helping attract customers and further investment. Prolonged restrictions on productive expansion could forgo both current construction orders and future business opportunities.

Existing U.S. computing and technological capabilities would not disappear because fewer facilities were built. China also needs to coordinate electricity, advanced chips and cluster operations. Large generating capacity does not automatically become high-performance AI computing. Effective delivery and commercial returns remain central to the outcome.

6. Which projects should wait, and who pays to keep building?

On November 5, OpenAI released a new National Community Compact. For future campuses it owns and operates, the company committed to paying the full cost of the power it uses and the incremental infrastructure needed to serve those campuses. It also committed to financial assurances before major spending begins, to prevent costs being left with other electricity customers if a project is delayed, downsized or canceled.

This establishes an important responsibility for continued construction. Whether the commitment protects other users will depend on local agreements, rate allocation and enforcement of financial assurances. A company's willingness to pay also does not replace the need to deliver generation and grid infrastructure on time.

AEP Ohio already has a specific connection arrangement: if a project is canceled before its target energization date, or delayed by more than 12 months, the customer must reimburse 100% of the relevant utility buildout costs. This is a contractual requirement in a particular service territory, illustrating one way to allocate project exit costs.

Local pauses can serve a useful purpose. Verifying demand, securing power resources and screening out projects without confirmed customers or financing can reduce wasteful investment. Even after substantial early spending, additional investment must still be compared with expected future returns. Money already spent is not, by itself, a reason to keep building.

A permitting pause does not automatically eliminate contracts, financing costs or completed grid infrastructure. If promised demand never arrives, responsibility for the remaining costs should be agreed in advance among developers, utilities and other customers, rather than negotiated only after a project exits.

Construction will continue. Power and cost responsibility must keep pace.

Projects that proceed should have verifiable customer demand, phased electricity requirements and deliverable power supply plans, with responsibility for reserved capacity, dedicated connections and exit costs agreed in advance. Some facilities may reduce or shift load under contract when the system is tight, provided their operations allow it. On-site generation also requires equipment, fuel and approvals. An annual power purchase agreement alone does not guarantee reliable electricity in every hour.

At the macroeconomic level, data center investment supports equipment orders, construction and digital services. Higher electricity bills can also raise other businesses' costs and squeeze household consumption. A reasonable purpose for local pauses is to verify demand, secure supply and clarify cost responsibility, allowing viable projects to proceed while poorly supplied or commercially uncertain projects adjust.

Considering existing demand and long-term U.S.–China technological competition, my judgment is that the United States should not impose a nationwide, prolonged halt on AI data center construction, and this round of tighter permitting will not stop computing expansion across the industry. OpenAI's commitment offers one route to resolving cost disputes. Some projects will be delayed, changed or abandoned, while construction continues. The central task is to align construction schedules, reliable power and responsibility for costs.

Data & sources

Sources are separate from the article. Applications, construction plans, operating facilities and forecasts are distinct. Capital expenditure uses global company-reported measures; observed electricity price changes do not identify AI causation.